THE SHORT ANSWER
The lead row in your water report gives the 90th percentile of tap samples taken inside selected homes. Nine in ten samples were at or below that number. Under the rules utilities follow today, the system has an action level exceedance if that number is above 15 ppb, which is the same as more than 10% of samples going over 15 ppb (40 CFR 141.80, July 1, 2020 version; EPA). The 15 ppb figure is a trigger for utility action. It isn't a safe level: EPA's health goal for lead is zero. The number also can't tell you what's coming out of your own faucet.
FAQ (quick)
- What does "90th percentile" mean? Line up every sample from lowest to highest. The 90th-percentile value is the one that 90% of the samples are at or below.
- Is 15 ppb a safe limit? No. It's an action level, the point that "triggers treatment or other requirements." EPA's goal (MCLG) for lead is zero.
- How can homes be over 15 ppb if the utility "passed"? The test applies to the 90th percentile, not to each home. A few sites can be over 15 ppb as long as they're no more than 10% of the samples.
- Is the action level changing? Yes. The current federal rule lowers it to 10 ppb (0.010 mg/L), with a compliance date of November 1, 2027.
- Does my report show lead in my house? No. It summarizes the utility's sample sites. Only a test of your own tap can tell you that.
How to read the lead row, column by column
Federal rules require each report to show "the 90th percentile concentration of the most recent round(s) of sampling, the number of sampling sites exceeding the action level, and the range of tap sampling results" (40 CFR 141.153(d)(4)(vi)).
| Column | What it means |
|---|---|
| Dates of sampling | The round the result comes from. This is often a year or more before the report, because many systems sample less than once a year (see below). |
| AL exceeded (Y/N) | "Y" only if the 90th percentile is above the action level. |
| 90th percentile result | The headline number, in ppb for lead (ppm for copper). |
| No. of sites exceeding the AL | How many sampled homes were above 15 ppb. This can be above zero even when the AL column says "N." |
| MCLG | 0 for lead. This is EPA's health goal, not an enforceable limit. |
| AL (action level) | 15 ppb for lead and 1.3 ppm for copper in 2025 reports. |
| Likely source | Usually "Corrosion of household plumbing systems; erosion of natural deposits." |
How the 90th percentile is calculated
The rule utilities follow until November 1, 2027 spells it out (40 CFR 141.80(c)(3), as of July 1, 2020):
- Put every lead result from the monitoring period in order from lowest to highest, and number them starting at 1.
- Multiply the number of samples by 0.9.
- The result in that numbered spot is the 90th-percentile level.
For example, if a utility took 30 samples, 30 × 0.9 = 27, so the 27th-lowest result is the 90th percentile. (This is an illustration, not any local utility's sample count.) Very small systems that collect only 5 samples use the average of the two highest results instead.
The samples aren't random. Under the 2020 rule, each is a first-draw, one-liter sample that has "stood motionless in the plumbing system of each sampling site for at least six hours," taken from a cold-water kitchen or bathroom tap (40 CFR 141.86(b)(2), as of July 1, 2020). EPA says utilities sample "sites served by the system that are more likely to have plumbing materials containing lead." The City of Sarasota's report says its samples "were taken in customer's homes after sitting in contact with copper pipes with tin-lead solder for 6-8 hours."
What local 2025 reports show
| Utility (2025 report) | Lead, 90th percentile | Sites over 15 ppb | Sampled | Action level exceeded? |
|---|---|---|---|---|
| North Port Utilities (city system) | 3.3 ppb (the report prints a second North Port row at 1.9 ppb) | 0 | July 2025 | No |
| Peace River Authority (row printed in the North Port and CCU reports) | 2.5 ppb | 0 | August 2023 | No |
| Charlotte County Utilities | 9.6 ppb | 4 | June 2023 | No |
| Englewood Water District | 6.08 ppb | 1 | July–Aug 2023 | No |
| City of Sarasota | 1.0 ppb | 0 | June 2025 | No |
| Sarasota County Public Utilities | 0.5 ppb | 0 | 2023 | No |
Sources: North Port Water Quality page (2025 report); CCU Peace River 2025; EWD 2025; City of Sarasota 2025; Sarasota County 2025.
Reading the table
- Every row is under 15 ppb, so none is an exceedance. That's the compliance test, and every utility here passed it.
- CCU and EWD had individual homes above 15 ppb: 4 sites and 1 site. That's allowed under the 90th-percentile test, but it's the reason a single home's result can look nothing like the headline number. More on CCU: Charlotte County lead service line inventory.
- Look at the dates. Four of the six rows come from 2023 sampling. Under the 2020 rule, a small or medium system that meets the action levels for three consecutive years "may reduce the frequency of monitoring for lead and copper from annually to once every three years," and a larger system can do the same with state approval if it keeps its corrosion-control water quality parameters in range (40 CFR 141.86, as of July 1, 2020).
- Why summer dates? Under the same rule, systems sampling annually or less often "shall conduct the lead and copper tap sampling during the months of June, July, August, or September" unless the state approves a different period. Every row above that prints a month falls in that window (Sarasota County's prints only the year).
- Compare utilities with care. Each system picks sites from its own pool of homes that are more likely to have lead plumbing materials, so the numbers measure different housing stock.
What changes on November 1, 2027
EPA's Lead and Copper Rule Improvements (LCRI) are already in the eCFR. The new text says the lead action level "is exceeded if the 90th percentile concentration of lead ... is greater than 0.010 mg/L" (10 ppb), and systems must comply "no later than November 1, 2027." Until then, they follow the rule "as codified on July 1, 2020" (40 CFR 141.80(a)(3)–(4), (c)(1)). The new rule also changes how samples are counted at homes with lead service lines: it uses "the higher of the first-liter and fifth-liter lead sample results." A future 90th-percentile number may therefore not compare directly with today's. The LCRI is being challenged in court, so check EPA's LCRI page for updates; our North Port lead service line guide tracks the case.
What to do at your own tap
Every water report has to carry the same lead statement. Among other things, it says to "use only cold water for drinking, cooking, and making baby formula," that "boiling water does not remove lead from water," to flush your pipes before drinking, and that "using a filter, certified by an American National Standards Institute accredited certifier to reduce lead, is effective in reducing lead exposures" (40 CFR 141.154(d)(1)).
- Look up your service line. See North Port lead service line lookup or Charlotte County lead service line inventory.
- Test your own tap if you're concerned. Your utility's report lists who to call. Lab options: water testing cost in Sarasota and Charlotte and North Port water testing.
- If you choose a filter, check the certification for lead reduction on the exact model. See choosing a filter for lead and how to read a filter certification.
FAQ
Did North Port go over the lead action level? No. North Port's 2025 report shows a 90th percentile of 3.3 ppb from July 2025 sampling, with 0 sites over 15 ppb. The same table prints a second North Port row at 1.9 ppb without explaining it, so we show the higher number. More: North Port water quality report.
Why is my utility's lead result from 2023? Systems that stay under the action levels can sample less often, as rarely as once every three years. The report prints the most recent round.
What does the copper row mean? The same thing, for copper. The action level is 1.3 ppm, and every local 2025 row above shows 0 sites over it.
Is there an MCL for lead? No. EPA set a treatment technique instead "because lead contamination of drinking water often results from corrosion of the plumbing materials belonging to water system customers."
Does showering in water with lead matter? EPA says "bathing and showering should be safe for you and your children, even if the water contains lead over EPA's action level," because "human skin does not absorb lead in water."
Next step
Want help reading your report's lead row, or choosing a drinking-water system with a lead-reduction certification? Schedule an in-home water check, or call 941-294-5767. More: How to read your water quality report · North Port drinking water · Under-sink reverse osmosis · Related: Turbidity on your water report
Sources
Drafted 2026-11-18 (America/New_York). Last fact-checked: 2026-11-18 (America/New_York).
- eCFR, 40 CFR 141.80 (current, LCRI text; compliance date and 0.010 mg/L action level)
- eCFR, 40 CFR 141.80 as of July 1, 2020 (0.015 mg/L action level, 90th-percentile steps)
- eCFR, 40 CFR 141.86 as of July 1, 2020 (first-draw samples, reduced monitoring)
- eCFR, 40 CFR 141.153 (CCR content)
- eCFR, 40 CFR 141.154 (required lead statement)
- EPA, Basic Information about Lead in Drinking Water
- EPA, Lead and Copper Rule Improvements
- North Port Utilities, 2025 Annual Report (via Water Quality page)
- Charlotte County Utilities, Peace River 2025 Water Quality Report
- Englewood Water District, 2025 CCR
- City of Sarasota, 2025 Water Quality Report
- Sarasota County Public Utilities, 2025 CCR
PLANNING A NORTH PORT INSTALLATION?
Turn your questions into a clear scope.
Review the home details, equipment questions and ongoing care to discuss before booking. Address coverage and scheduling are confirmed during your callback.
View the North Port installation guideA PRACTICAL NEXT STEP
Drinking water, explained.
Fresh-tasting water for every glass, pot of coffee, and family recipe.
Explore this solution